| Cost saving # 1: The drawings of the hinge fabrication were first shown to
us using a solid a profiled blank for the inner hinge, to machine 2# 50mm
diameter holes,
the tapered hole was particularly cost restrictive. Proposal: The components could be manufactured as fabrications and that the bosses could be pre-machined and assembled in jigs to produce the finished component. Result: An estimated cost saving in the first year of £20000 which ultimately led to our customer's product being more marketable. The benefit to both parties is immense. |
![]() |
| Cost saving # 2: The original drawing of the oil sampling valve showed a valve body machined from a solid billet. Proposal: To manufacture using pre-machined parts. Result: We saved our customer approximately £16.00 per item against the previous suppliers. The total annual saving approximately £1920.00. |
![]() |
| Cost saving # 3: The drawing of a Rubbing plate shows the
parallel flange channel sections in eight parts of four different lengths. Proposal: To cut the relief's into the pressed steel angle cross members at the profiling stage. Result: We are able to saw cut the parallel flange channel in two parts eliminating sawing, handling, and assembly time. The annual cost saving to our customer is worth approximately £5000.00. |
![]() |